Example projects  with very good environmental performance

Building water quality from an environmental quality office

It is not surprising that ground and hydraulic engineering company GMB is outgrowing its scope. With water quality and water safety becoming increasingly important, a growing number of drinking water companies, water boards, municipalities and provinces are knocking on the door of the family-owned company that designs, builds and maintains dikes, port sites, sewers, pumping stations, water purification plants and sludge treatment plants. To meet the growing demand, GMB now has several branches. With the headquarters in Opheusden in the Betuwe region becoming too small to work well together, plans have been developed for a new headquarters in Dodewaard.


"We work on sustainable solutions for water safety and water quality. For it makes sense to us that those solutions start with good cooperation at the drawing board of a sustainable office,’ reports Gerrit-Jan van de Pol, director of GMB. "When we decided to build a new head office, it was our intention from the outset to do so with great attention to CO₂ emissions, the environmental quality of the materials and their effects on people and nature in the surrounding area. Leaving your old place after 60 years, you only do that when it is good for the company as well as for our employees and the environment. "

Gerrit-Jan van de Pol says that the design came about thanks to good cooperation between the members of the construction team (see Project features). With such a high level of ambition, it is necessary to get all parties involved as early as possible. amen with GMB Civiel joined forces to create a unique design."

GMB's new building in Dodewaard comprises an office building, a yard with three outbuildings and plenty of parking and loading facilities, situated in a robust green setting. H t whole is situated in the extension plan of the Bonegraaf business park along the A15 motorway.

Project features  
Project name Nieuwbouw GMB hoofdvestiging
Use function Office
Adress Bonegraaf Oost
Gross floor area 2929 m2
Building service life 85 years
Delivery To be determined
Client

GMB

Architect ARCOM Partners Architectuur + bouwmanagement
Constructor IMd Raadgevende Ingenieurs
Building contractor Aan de Steffe Twello
Installer Hollander Techniek
Landscape architect Buro Ontwerp & Omgeving
Site GMB Civiel
V&G B&V Advies
Advisor

Merosch, advisering m.b.t. installaties, duurzaamheid, bouwfysica en brandveiligheid 

   

 

The process of developing a sustainable building took time and effort, says sustainability consultant Peter Stam of Merosch. The project started on the basis of a concrete-steel construction. GMB then asked Merosch to test the preliminary design against their sustainability ambitions.  

Artist impression new GMB Dodewaard building.

"First, we carried out a baseline measurement by calculating the preliminary design using BENG, MPG, Paris Proof and GPR building. This showed that the design did not meet GMB's sustainability ambitions. We then drew up improvement proposals based on timber construction and bio-based variants. For inspiration, we organised a bus tour of various timber construction projects. The bus tour played an important role in gaining support for building with wood. That tour inspired everyone and helped make it a success."
The core of the sustainability concept is that the building will be constructed largely from wood, the energy required will be generated from renewable sources, the building will be demountable and adaptable, and the site will be landscaped from nature-inclusive building guidelines.

Artist impression new GMB Dodewaard building

The timber construction includes beams and girders, timber hollow-core slab floors, precast HSB façade elements fitted with timber frames with an aluminium top layer and the cladding. ‘Working with wood contributes to a low environmental impact, ensures the retention of biogenic CO₂ in the building, makes the foundation lighter, promotes a healthy indoor climate and, thanks to the beam and column structure, offers many possibilities for extensions and modifications,’ Peter Stam states. He is particularly enthusiastic about the wooden hollow-core slabs. Their cost is high, but according to Peter, the hollow-core slab floor has high added value. "No suspended ceiling is installed, thus avoiding costs and materials. The ventilation ducts are fitted between the hollow-core slabs, remain visible and are easily adjustable. For acoustics, the floor elements are perforated at the bottom."

Peter Stam regrets that Lignatur's hollow-core slab floor could not be included in the MPG calculation. "We had to designate a category-3 product because this floor does not have a category-1 declaration. That is a pity, otherwise the MPG score would have been even better. We will therefore work with the supplier to provide the floor with a category-1 statement." Peter Stam therefore also calls on the market to register as many building materials and installations as possible in the NMD. He also regrets that the calculation does not value the biogenic storage of CO₂ in wood products. "The calculation assumes that all biogenic CO₂ stored in the wooden construction is released again through combustion. Instead, the wooden construction lends itself to reuse and long-term storage of biogenic CO₂."

The building is fitted with a high-quality thermal building envelope and equipped with sustainable installations. Sustainable heat and cold comes from the ground. PV panels generate renewable energy for the buildings and for the electric commercial vehicles, while batteries provide energy storage. To keep out the heat from outside and reduce cooling demand, green vision screens, overhangs and automatic exterior blinds are installed.

Naturally for a hydraulic engineering company like GMB, attention is also paid to water. Rainwater is collected and reused for the toilets. Where possible, the site will be designed with semi-paving, infiltration facilities and wadis.

The plan now needs to be taken to the implementation phase, but so far GMB is enthusiastic about the plan. Project manager Henk Ruiterkamp says: ‘The design shows that we can work on our projects from our sustainable office in the near future. With in an MPG score of 0.685, good BENG scores and a GPR Gebouw score higher than 8.5 on all themes, we can be confident that, with our own input, we are ready for the future."

Key design features

 
Foundation

foundation beams, Betonhuis, cast-in-place concrete, C30/37, CEMIII, 20% concrete aggregate, incl. reinforcement and EPS (cat.2); with a 50% aggregate target;
underings piles, precast piles, AB-FAB, 290x290 mm and 320x320 mm (cat.2).

Ground floor

self-supporting floors, VBI hollow-core slab floor 260 Rc 4.0 green (cat.1);

anfilling insulation hollow-core slab floor IsoBouw EPS100-SE, Rc/d = 0.5 m²-K/W (cat.1);

kfloors, sand-cement (cat.3).

Main supporting structure

timber columns and beams, laminated European softwood, sustainable forestry, 117,723 kg (cat.3)

out beams at side wall overhangs, European softwood, sustainable forestry (cat.3);

aluminium columns and beams, prestressing steel, various structures, total 32,625 kg (cat.3);

onnen columns basement box, Concrete house, cast-in-place concrete, C30/37, CEMIII+20 concrete aggregate incl. reinforcement (cat.2), with target 50% aggregate.

Flooring

self-supporting floors, wood channel board flooring (cat.3), as equivalent input for wood channel board Lignatur;
KLH CLT solid floor (cat.1), CLT strips between Lignatur;
cladding, European softwood, sustainable forestry (cat.3), OSB on Lignatur;
insulation layers, IsoBouw EPS (cat.1);
suspended plasterboard ceiling (cat.2), equivalent of Ecophon Hygiene Performance A.

Cellar and elevator

floors structural, Betonhuis, in-situ concrete, C30/37, CEMIII+20 concrete aggregate incl. reinforcement (cat.2), starting point is to apply 50% aggregate;
EPS 100 SE floor slab (cat.1);
Solid walls, load-bearing, cast-in-place concrete, C30/37 incl. reinforcement (cat.3), with a target of 50% aggregate.

External wall

system walls, HSB prefabricated, incl. insulation, sustainable forestry (cat.2);
curtain walls, laminated larch, aluminium cover strip, powder-coated, sustainable forestry (cat.3); excl. glass, hinges and locks, hinged parts and frames;
insulation layers, glass wool (cat.3), in addition to HSB up to Rc-value 6.5;
cladding with fibre cement board (cat.3), cladding with parts European softwood with wax impregnation, sustainable forestry (cat.3), cladding with glass, plate+steel profiles (cat.3), equivalent to AGC Colorbel panel.

External facade windows

insulation glass coating, triple silver, Bouwend Nederland Vakgroep Glas (cat.2), 90% of window frames and main entrance;

solation glass, triple silver, uncoated, Bouwend Nederland Vakgroep Glas (cat.2), 90% of window frames and main entrance.

Outdoor sun protection

Solidscreen XS hood 105 (cat.1).

Roof

self-supporting floors, wooden hollow-core slab floor (cat.3);
NVPU, PIR board, capped with alulaminate flat roof insulation Rd-6.0 (cat.2);
flat roofing, Stg. Dak en Milieu, bitumen modified single-ply, fully bonded, fire method system (cat.2), Wienerberger Leadax Roov;
roof finishes, gravel (cat.3), ballast layer Lignatur floor.

Interior walls

non-loadbearing relocatable partitions, wooden frame, single-glazed (cat.3), glazed partitions incl. doors
gypsum fibreboard partition wall 100 mm, double panelled with 40 mm glass wool (cat.2), partition walls 60 minutes
gypsum fibreboard partition wall 100 mm, single ply with 60 mm glass wool (cat.2), partition walls standard;
non-loadbearing system walls, HSB precast, sustainable forest management (cat.2), closed system wall between offices;
cladding system wall non-load-bearing, plasterboard (cat.3), additional cladding HSB façade.

Stairs

central staircase, coated steel with meranti treads, sustainable forestry (cat.3).

Elevators lift, cabs and installations, steel (cat.3).
Heat generation

heat distribution systems, polyethylene/polybutene (cat.3), thin-walled steel version (Mapress);

water pump, 10kW settled (cat.3), total water-water WP = 45 kW.

Ventilation

Air handling system VLA BLK, balance (cat.2), 15,000 m³/h;
Air distribution system, mechanical supply and return, galvanised steel incl. diffusers (cat.3)

Cooling cold delivery systems, floor cooling/wall cooling (cat.3);
cold delivery systems, ducts and grilles for top cooling (cat.3).
Elektric installations

energy low voltage installation incl. distribution (cat.3);
Sunpower Maxeon 3 monocrystalline photovoltaic module (cat.1), 20 units serving BENG requirements and GPR = 8.5;
Grid electricity, NL-mix, 1 kWh (lump sum) (cat.3a).

Lighting fixture and lamps, LED 120 cm (cat.3).

 

MKI AND MPG SCORE NEW GMB HEADQUARTERS TO BE BUILT AT DODEWAARD 
calculated with GPR Material version 5, product database NMD, version 3.0, product database 12 July 2023.

    MKI MPG
A Production phase 104.738,111 0,422
A Construction phase 7.884,250 0.032 htn: switched off
B User phase 77.779,057 0,313
C Abandoment phase -2.740,498 -0,011
D Pu of building life demolition -17.554,893 -0,071
   

170,106

0,685